Generator sizing

Generator + UPS Compatibility Checker

Right-size a backup generator for a UPS — with the correct rectifier-topology multiplier, step-load check against the governor, and altitude / temperature derating.

Recommended generator
200 kVA
= 160 kW (ISO 8528, 0.8 PF)
Step load on rectifier start
85%
Exceeds 80% electronic governor capability
Topology multiplier
×1.40
6-pulse SCR with passive filter (~10% THDi)
Total demand (before derating)
136.0 kW
UPS 126.0 + recharge 10.0 + other 0.0
Site deratings
100%
Altitude 100% × temp 100%

Why this number, not the UPS nameplate

A 100 kVA online UPS with a 6-pulse SCR rectifier and no filter draws roughly 286 kW from the genset during startup — almost 3× its rated output. The harmonic current fights the alternator's reactance, the bus voltage sags, the rectifier tries to compensate, and the loop oscillates. Sizing the genset on UPS nameplate kVA alone is the most common cause of dropped-load events on backup generators.

Important notes

  • UPS rectifier start applies a 85% step — exceeds the electronic governor's 80% maximum. Use a larger generator, soft-start the UPS rectifier, or specify an electronic governor.

Quote the right genset the first time.

Power Stack tracks the rectifier topology and step-load profile of every UPS in your installed base, so genset retrofits and renewals get sized from real fleet data instead of from memory.

Start free

The five things that drive genset size

UPS-on-genset is one of those installations where the components are individually correct but the combination misbehaves. The cure is to size the genset based on the worst-case dynamic load the UPS presents, not the UPS's steady-state output rating. Five factors set the answer.

1. Rectifier topology

The dominant variable for an online double-conversion UPS. A 6-pulse SCR rectifier with no input filter generates roughly 30% total harmonic distortion on the input current. That distortion forces a 2.5–3× upsizing of the genset just to avoid voltage collapse during the rectifier's soft-start ramp. A passive input filter (typically a 5th/7th harmonic trap) or a 12-pulse rectifier cuts the distortion to about 10%, dropping the multiplier toward 1.4×. IGBT (active-front-end) rectifiers stay under 5% distortion and need only ~1.25× the UPS kW. The difference between “6-pulse no filter” and “IGBT” is roughly half the generator capital cost.

2. Battery recharge

The UPS starts recharging the battery the instant grid is restored, then again whenever the genset picks up. The recharge load is typically about 10% of UPS kVA, in addition to the steady-state load. Worst case: the genset starts under full UPS load and the battery is depleted — both arrive at the bus simultaneously.

3. Other loads on the same bus

Almost every site has more than just the UPS on the genset — air conditioning, lighting, fire pumps, elevators, motorised dampers. These don't step-load the genset (they're running before the UPS picks up), but they do consume real kW. Add them in.

4. Governor step-load capability

Diesel governors are rated for the largest single instantaneous load they can absorb without dropping frequency. Electronic isochronous governors handle 50–80% step loads in one bite. Mechanical (older or smaller gensets) handle 25–35%. If the UPS rectifier inrush + recharge exceeds the governor's step-load rating, the genset will trip on under-frequency before the UPS finishes its soft-start. The fix: a larger genset, an electronic governor, or a UPS soft-start setting that ramps the rectifier over several seconds.

5. Altitude and ambient temperature

Naturally-aspirated diesels lose roughly 1% of rated output per 100 m above 1000 m, and 2% per 5 °C above 25 °C ambient. A 200 kVA genset at 2000 m elevation and 40 °C is really a 168 kVA genset. Turbocharged engines derate more gently — confirm with the vendor. For sites in hot, high regions (Andean plateaus, parts of East Africa, central Iran) the derating can swallow an entire size step.

Standards behind the math

Topology multipliers from Eaton TD00405018E and Generac Power Systems sizing guidance. Step-load ranges from Cummins / Kohler governor datasheets. Altitude/temperature derating from ISO 8528-1 Annex C. Generator kVA-to-kW conversion at 0.8 PF lagging per ISO 8528.

Engineering disclaimer: Power Stack provides this calculator as a general engineering estimate. Final design must be verified by a qualified electrical engineer and reconciled with manufacturer datasheets, the applicable national wiring regulations (NEC, BS 7671, IEC 60364, or your local equivalent), and site-specific conditions. Power Stack accepts no liability for design decisions made from this output.